40-Year Delayed Islamabad Sector Near Margalla Hills Almost Ready
Meanwhile, the Capital Development Authority (CDA) has completed more than 68 percent of development work in Islamabad's Sector E-12, almost four decades after the project was first delayed.
Meanwhile, the Capital Development Authority (CDA) has completed more than 68 percent of development work in Islamabad's Sector E-12, almost four decades after the project was first delayed.
Article outline
- What happened
- The details
- Official response
- The bottom line
Key points
- While earthwork has been completed on the remaining streets, in Sector E-12/1, TST work has been completed on 25 streets.
- While earthwork and base work are continuing elsewhere, in E-12/3, TST work has been completed on 15 streets.
- Development work in E-12/4 is additionally underway, with earthwork completed and base, sub-base, drainage and sewerage work in progress.
- CDA has additionally kicked off asphalt work on Service Road Khayaban-e-Iqbal after completing earthwork, base, sub-base and drainage infrastructure.
- To remove obstacles to the project, CDA has reclaimed around 1, 135 kanals of land from illegal occupation.
In practice, the authority has additionally kicked off handing over possession of plots to allottees in areas where infrastructure development has been completed, allowing them to commence construction of their houses.
According to CDA, it has received a number of applications from allottees seeking possession of their plots. IHC Tells CDA to Fix Islamabad's Stray Dog Difficulty.
While earthwork has been completed on the remaining streets, in Sector E-12/1, TST work has been completed on 25 streets. In E-12/2, TST work is complete on 31 streets, with earthwork and base work finished in the remaining areas.
CDA has additionally kicked off asphalt work on Service Road Khayaban-e-Iqbal after completing earthwork, base, sub-base and drainage infrastructure. While asphalt work is progressing on Margalla Road alongside the sector, work on Service Road East has reached the same stage. Underground infrastructure for electricity supply is additionally being developed.
To remove obstacles to the project, CDA has reclaimed around 1, 135 kanals of land from illegal occupation. Landscaping and plantation along green belts are additionally underway.
CDA Chairman has directed relevant departments to resolve outstanding problems and complete the remaining development work on a priority basis.
Meanwhile, the authority notes development of new residential sectors is a priority to address Islamabad's growing housing demand. Stay Connected with ProPakistani.