Karachi’s Biggest Water Pipeline Project Misses Another Deadline
Karachi's long-delayed greater Karachi bulk water supply scheme, better known as K-IV, is now projected to be completed by June 2027, WAPDA office-holders informed a National Assembly sub-committee on Wednesday.
Karachi's long-delayed greater Karachi bulk water supply scheme, better known as K-IV, is now projected to be completed by June 2027, WAPDA office-holders informed a National Assembly sub-committee on Wednesday.
Article outline
- What happened
- The key numbers
- What comes next
- Official response
- The bottom line
Key points
- While WAPDA assumed responsibility in April 2021 and began mobilisation in September 2022, the federal administration took up the project under the Karachi Transformation Plan in 2020.
- The scheme was initially scheduled for completion by October 2023, but its revised target now stands at June 2027.
- The sub-committee of the National Assembly Standing Committee on Water Resources, chaired by Muhammad Idrees, reviewed the project's implementation, design complications, planning, and reasons for the delays.
- WAPDA authorities stated Karachi's water requirement stood at around 1, 200 MGD, highlighting the project's importance in bridging the city's widening supply gap.
- Upon completion, Karachi Water and Sewerage Corporation would take over the operation and maintenance.
Meanwhile, the lawmakers questioned the repeated delays and sought accountability for the project's slow progress.
Notably, the sub-committee of the National Assembly Standing Committee on Water Resources, chaired by Muhammad Idrees, reviewed the project's implementation, design complications, planning, and reasons for the delays. Newly-Built 6-Floor Building Collapses in Karachi.
Members expressed concern over the prolonged execution of the scheme, stressing that it was critical to session Karachi's growing water needs and that no further delays should be allowed.
They additionally sought details of action taken to fix responsibility for the setbacks, noting that both the federal and Sindh governments had attached importance to the project. A 24-Year Journey of Setbacks.
Briefing the committee, WAPDA authorities stated the project was conceived by the Sindh administration in 2003 to address Karachi's growing demand for potable water and reduce its supply deficit.
Civil works began in July 2016 under a contract awarded to the Frontier Works Organization (FWO), but the original December 2018 completion deadline was missed after design-related challenges emerged.
Notably, a third-party investigation commissioned by the Sindh administration subsequently identified shortcomings in the design. Rs. 5 Billion Rawalpindi Overhaul: What's in the Package.
For context, the scheme was initially scheduled for completion by October 2023, but its revised target now stands at June 2027. Authorities stated the revised design and planning had been submitted to the Planning Commission and the federal administration. The 650 MGD Supply Plan.
Originally planned to deliver 650 million gallons per day (MGD) from Keenjhar Lake in Thatta to Karachi in three phases, the scheme envisages 260 MGD under Phase-I, another 260 MGD in Phase-II, and 130 MGD in Phase-III.
Meanwhile, the first phase, being executed by WAPDA under the Ministry of Water Resources, is designed to supply 260 MGD through three termination points at Pipri, North East Karachi, and Manghopir.
Its infrastructure includes an intake structure at Keenjhar Lake, a gravity channel, pumping facilities, a pressurized pipeline, three reservoirs, and filtration plants.
Notably, the Sindh administration is responsible for the distribution and augmentation network, power arrangements, land acquisition, and right-of-way clearance. Bridging a Widening Supply Gap.
WAPDA authorities stated Karachi's water requirement stood at around 1, 200 MGD, highlighting the project's importance in bridging the city's widening supply gap. Murree Intends New Restrictions on Vehicle Entry During Snowfall.
In practice, the session was attended by MNAs Waseem Hussain, Javed Ali Shah Jilani, Mian Khan Bugti, and Amin-ul-Haque, along with Further Secretary Water Resources Mehar Ali Shah, K-IV Adviser Engineer Amir Mughal, Project Director Gul Mir Khan, and other authorities. Stay Connected with ProPakistani. Obtain the latest news and stories wherever you prefer. Follow on Google Discover. Follow on Google News Join WhatsApp. See more ProPakistani stories in Google Search and Top Stories.
Taken together, the developments around karachi's Biggest Water Pipeline Project Misses Another Deadline point to a situation that is still moving, and the coming days should bring more clarity.