Guddu Power Plant Turbine Rehab to Restore 297 MW, Cut Cost by Rs. 4.19 Per Unit
In practice, the administration has invited international competitive bids to rehabilitate the fire-damaged Steam Turbine 16 at the Guddu 747 MW Power Plant, a project anticipated to restore 297 MW of generation capacity and reduce the plant's generation cost by…
In practice, the administration has invited international competitive bids to rehabilitate the fire-damaged Steam Turbine 16 at the Guddu 747 MW Power Plant, a project anticipated to restore 297 MW of generation capacity and reduce the plant's generation cost by Rs.
Article outline
- What happened
- The key numbers
- The details
- The bottom line
Key points
- Add ProPakistani to Preferred Sources and see more of our stories in Google Search and Top Stories.
- The steam turbine and its associated generator have remained out of service since a fire incident in July 2022.
- Once ST 16 is restored, the plant is projected to return to full combined cycle operation and reach its designed output of 747 MW.
- The rehabilitation would add 297 MW to the plant's current output, representing an growth of concerning 66 percent.
- Add as a preferredSource on Google Follow on Google News Join WhatsApp.
For context, the rehabilitation is projected to bring the plant's generation cost down from Rs. 13.87 per unit to Rs. 9.68 per unit. The Power Division remarked the procurement process covers ST 16 and allied equipment and has been structured as an EPC turnkey project. IMF Tells Pakistan Govt to Stop Awarding Contracts to Itself.
Meanwhile, the steam turbine and its associated generator have remained out of service since a fire incident in July 2022. The plant has consequently been operating in open cycle mode at around 450 MW and at present ranks around 11th in the dispatch merit order as of its relatively high generation cost.
After technical studies, integrity assessments and an engineering review, the Power Division has initiated the international competitive bidding process. While rehabilitation works are targeted for commissioning by December 2028, the deadline for bid submissions has been set for October 7, 2026.
Once ST 16 is restored, the plant is projected to return to full combined cycle operation and reach its designed output of 747 MW. Its position in the dispatch merit order could additionally improve to approximately seventh, allowing the system operator to replace more expensive sources of electricity.
Meanwhile, the rehabilitation would add 297 MW to the plant's current output, representing an growth of concerning 66 percent. The Power Division remarked the further lower cost generation would allow the administration to produce greater employ of an existing power asset rather than relying solely on new generation capacity.
In practice, the project is additionally considered notable for the national transmission system since Guddu is located at a key point in the north south power flow corridor. Stay Connected with ProPakistani.
Obtain the latest business news, market insights, and economic updates wherever you prefer. Follow on Google Discover.
In short, guddu Power Plant Turbine Rehab to Restore 297 MW, Cut Cost by is the central thread here, and readers can expect follow-up reporting as the picture becomes clearer.