Pakistan’s Reko Diq Project Faces $2.1 Billion Cost Hike: Report
While initial production could be delayed by two years to 2030, according to a report published by the Institute of Cost and Management Accountants (ICMA), pakistan's Reko Diq project has seen its estimated development cost jump 30 percent to $9.1…
While initial production could be delayed by two years to 2030, according to a report published by the Institute of Cost and Management Accountants (ICMA), pakistan's Reko Diq project has seen its estimated development cost jump 30 percent to $9.1 billion from.
Article outline
- What happened
- The key numbers
- Why it matters
- The details
- Reaction
- The bottom line
Key points
- The figures highlight the growing financial exposure of Oil and Gas Development Firm Limited (OGDCL), Pakistan Petroleum Limited (PPL), and Administration Holdings (Private) Limited (GHPL).
- Although Barrick has not formally confirmed a revised production date, initial production, originally targeted for the end of 2028, could now shift to 2030.
- The rising costs come as Reko Diq faces development uncertainty after security worries in Balochistan.
- The project is designed around a 37 year mine life and a two phase development plan.
- The report highlights that Reko Diq is at present designed to produce copper and gold concentrate, with smelting and refining outside the project's existing scope.
In practice, the rising cost tag and potential delays are increasing financial risks for three Pakistani state-owned enterprises (SOEs) that have committed approximately $1.88 billion to the mining project.
In practice, the figures highlight the growing financial exposure of Oil and Gas Development Firm Limited (OGDCL), Pakistan Petroleum Limited (PPL), and Administration Holdings (Private) Limited (GHPL). It collectively own 25 percent of Reko Diq. While the Administration of Balochistan owns the remaining 25 percent, international mining firm Barrick holds a 50 percent stake. Pakistan Expects $700 Million Investment in 7 Cement Plants. Reko Diq's Development Cost Rises to $9.1 Billion.
While Phase II costs have risen from $3 billion to $3.5 billion, according to a report published by the Institute of Cost and Management Accountants (ICMA), the project's Phase I investment estimate has rose from $4 billion to $5.6 billion.
Notably, the project is designed around a 37 year mine life and a two phase development plan. Phase I is projected to process 45 million tonnes of ore annually, with capacity increasing to 90 million tonnes under Phase II. Security Reservations Add to Project Delays.
For context, the rising costs come as Reko Diq faces development uncertainty after security worries in Balochistan. Barrick initiated a review of the project in February 2026 and confirmed a slowdown in development in April, extending the review until mid 2027 to reassess security conditions, financing, capital requirements, and project timelines. HUBCO Eyes 300, 000-Tonne Aluminium Smelter.
Although Barrick has not formally confirmed a revised production date, initial production, originally targeted for the end of 2028, could now shift to 2030. While estimates of extra capital requirements remain uncertain, the firm has additionally cautioned that previously disclosed project costs and schedules could change.
For Pakistan's participating SOEs, the delays could postpone dividend income, growth financing exposure, and raise the opportunity cost of committed capital. The rising investment requirements additionally produce cost controls, transparent monitoring, and timely project execution increasingly significant. Reko Diq Could Generate $74 Billion in Cash Flow.
Despite the financial risks, the project carries significant long term economic potential. It is estimated to generate approximately $74 billion in free cash flow over its projected 37 year mine life, with peak construction employment of 7, 500 workers and around 4, 000 permanent jobs. Govt Proposes Fixed Dollar Rates for Jewellery Exports.
Nevertheless, the projected cash flow should not be confused with revenue directly accruing to Pakistan. Actual economic benefits will depend on ownership distributions, taxes, royalties, reinvestment, and the participation of domestic businesses in the project.
Notably, the development could strengthen mineral exports, generate administration revenues, and create demand for local engineering, construction, transportation, and maintenance services. Workforce training could additionally improve technical capabilities and create opportunities beyond the mine's operating life. Domestic Processing Remains a Major Challenge.
Meanwhile, the report highlights that Reko Diq is at present designed to produce copper and gold concentrate, with smelting and refining outside the project's existing scope. This means domestic value addition is not guaranteed despite Pakistan's participation in the mining venture.
Developing local processing capabilities would depend on commercially viable access to energy, infrastructure, technology, and markets. Policymakers would additionally need to monitor local supplier participation, skilled employment, workforce training, administration revenues, and opportunities for domestic processing.
Reko Diq represents a potential shift in how Pakistan's state owned enterprises participate in the economy, moving beyond traditional operations toward strategic equity investments alongside international firms.
Nevertheless, the report argues that commercial viability must remain central to such decisions. Transparent disclosure of capital commitments, independent oversight, regular financial and operational assessments, and clear shareholder accountability will be essential to ensuring that the project generates measurable economic returns rather than becoming another financial burden on public enterprises. Stay Connected with ProPakistani.
Obtain the latest business news, market insights, and economic updates wherever you prefer. Follow on Google Discover. Follow on Google News Join WhatsApp. See more ProPakistani stories in Google Search and Top Stories.
Taken together, the developments around pakistan's Reko Diq Project Faces $2.1 Billion Cost Hike: Report point to a situation that is still moving, and the coming days should bring more clarity.