Rawalpindi Ring Road Opening Delayed Again

For context, the opening of the state-of-the-art Rawalpindi Ring Road project.

TechnologyNews Info Wire3 min read
Rawalpindi Ring Road Misses 6th Deadline

For context, the opening of the state-of-the-art Rawalpindi Ring Road project.

Article outline

  1. What happened
  2. Official response
  3. What comes next
  4. The key numbers
  5. The bottom line

Key points

  • 7.38 Billion on Solid Car Sales Oct 28, 2026 12: 12 pm.
  • K-IV Pipeline Work Once Again Delayed in Karachi Oct 28, 2026 12: 06 pm.
  • The Islamabad Ring Road project, linking Taxila to Bharakahu and Bharakahu to Rawat-Banth, has been given a completion deadline of June 30, 2028.
  • 52-KM-Long Diversion Confirmed on Major Motorway Oct 28, 2026 12: 32 pm.
  • While its foundation stone was laid by former prime minister Imran Khan, the project was conceived during the tenure of former Punjab chief minister Chaudhry Parvez Elahi.

For context, the opening of the state-of-the-art Rawalpindi Ring Road project. It has remained pending for almost two decades, has been postponed for the sixth time, with one interchange still incomplete and key tolling and traffic management systems yet to be installed.

For context, the toll booths, Intelligent Transportation System (ITS), and electronic toll collection system are additionally awaiting completion, further delaying the full operational launch of the project.

Initially estimated to cost Rs26.9 billion, the project has become a financial burden, with its cost now exceeding Rs58 billion and projected to approach Rs60 billion by completion. K-IV Pipeline Work Once Again Delayed in Karachi.

For context, the 38.3-kilometre road comprises six lanes and five interchanges. The Banth interchange, which marks the starting point, along with the Chak Beli Khan, Adiala Road and Chakri interchanges, has been completed. Nevertheless, the Thallian interchange, near the route's endpoint, remains unfinished.

Notably, the Rawalpindi commissioner has decided to ensure that the ring road is fully opened to traffic in November, with the aim of eliminating heavy traffic from the city and improving traffic flow. Pakistani Flags With Wrong Design Displayed in Islamabad.

Meanwhile, the Islamabad Ring Road project, linking Taxila to Bharakahu and Bharakahu to Rawat-Banth, has been given a completion deadline of June 30, 2028.

Once both projects are complete, a wider ring road network will connect Rawalpindi and Islamabad, enabling heavy vehicles travelling between Khyber Pakhtunkhwa, Azad Jammu and Kashmir, Gilgit-Baltistan and Punjab, including routes towards Karachi, to bypass the twin cities. Stay Connected with ProPakistani.

Obtain the latest automobile news, car launches, bike reviews, videos and analysis wherever you prefer. Follow on Google Discover. Follow on Google News Join WhatsApp. See more ProPakistani stories in Google Search and Top Stories.

Toyota Indus Motor Q1 Profit Jumps to Rs. 7.38 Billion on Solid Car Sales Oct 28, 2026 12: 12 pm.

For now, rawalpindi Ring Road Opening Delayed Again remains the part of the story worth watching, and further updates are likely as more details are confirmed.