Start work of additional railway lines from Attipattu to Gummudipoondi: Users
CHENNAI: Gummudipoondi Railway Passengers Welfare Association on Tuesday wrote to Prime Minister Narendra Modi, Railways Minister Ashwini Vaishnaw and senior railway authorities, requesting the commencement of work on the third and fourth railway lines from Attipattu to Gummidipoondi.
CHENNAI: Gummudipoondi Railway Passengers Welfare Association on Tuesday wrote to Prime Minister Narendra Modi, Railways Minister Ashwini Vaishnaw and senior railway authorities, requesting the commencement of work on the third and fourth railway lines from Attipattu to Gummidipoondi.
Article outline
- What happened
- What comes next
- The bottom line
Key points
- The 22.52-km-long third and fourth railway lines, to be laid at a cost of Rs 365.42 crore, were sanctioned by the railways lately.
- In his letter, S Suresh Babu, president of the association, remarked that approximately eight months after the Railway Board's approval, Southern Railway opened a tender.
- As of now, he remarked, suburban trains halt on loop lines at Ponneri, Minjur and Kavaraipettai stations after Attipattu to prioritise express trains.
- Our individuals are suffering greatly due to the existing railway congestion and prolonged travel time.
For context, the 22.52-km-long third and fourth railway lines, to be laid at a cost of Rs 365.42 crore, were sanctioned by the railways lately.
In his letter, S Suresh Babu, president of the association, remarked that approximately eight months after the Railway Board's approval, Southern Railway opened a tender. It closed on May 12, 2026. Almost five months have passed, but work has not yet kicked off, he noted.
"Our individuals are suffering greatly due to the existing railway congestion and prolonged travel time. Every day, passengers are compelled to spend almost two hours travelling just 45 km from Gummidipoondi to Chennai Central. The doubling project has been a long-pending demand of thousands of North Chennai residents. Once implemented, the travel time from Chennai Central to Gummidipoondi is projected to go down by approximately 45 minutes, " Suresh Babu stated.
He continued that the third and fourth lines from Korukkupet to Attipattu are mostly employed for goods trains rather than suburban trains, adding that if they are applied for sub-urban trains, travel time will be reduced. As of now, he remarked, suburban trains halt on loop lines at Ponneri, Minjur and Kavaraipettai stations after Attipattu to prioritise express trains. If the third and fourth lines are laid, there will be two dedicated lines for express and suburban trains, he remarked.
In short, start work of additional railway lines from Attipattu to Gummudipoondi: Users is the central thread here, and readers can expect follow-up reporting as the picture becomes clearer.